Agrimin Ltd

Key Statistics

Statistic Type Statistic Value
Biomass Boiler 301kW Herz Firematic
Previous Fuel Source LPG and electric
Current Heat Usage 185,000kWh’s
Fuel Type Wood pellet
Fuel Usage 62 Tonne
Back Up Boiler Potterton Eurocondense
Back Up Boiler Fuel LPG
CO2 Savings per Year 92 Tonnes
Projected RHI Payment per Annum £20,487.63
Fuel Savings per Annum £15,200.00 (estimated)
Projected Payback Time 4.5 Years

Project Summary

The customer required an alternative heating system for manufacturing process heat and space heating at their factory near Kirmington. It was essential that a stable heat source was provided, so a back-up LPG boiler was installed to be called upon in the event of biomass boiler down time.

With future development in mind we advised the installation of a 301kW Herz Firematic with an 8,000ltr buffer running at a high 85-degree temperature to suit the manufacturing processes.

To ensure that project timelines were achieved and a minimum of disruption occurred, the biomass and LPG boiler plant room was built within a purpose made container off site at our manufacturing area. The pellet store was supplied by Collinson days before the biomass container, with the connections and commissioning taking just 7 days to complete.

This particular project went very smoothly, as is often the case when a plant room is manufactured at our base in Newark, then delivered ready for connection to pre-prepared heating systems. J L Phillips have the capability to manufacture biomass containerized systems up to 999kW’s in size, with built in buffering and in some cases, built in wood chip or wood pellet stores.

Claim Your Free Quick Quote

Why not take a look at what a new renewable heating system might cost to install in your home or business. All we need is your preferred heating technology along with the approximate age and size of your property

Claim Quick Quote
01636 642790
info@jlphillips.co.uk
J L Phillips Renewable Energy Ltd, Fen Lane, Long Bennington, Newark, NG23 5ED