Key Statistics

Statistic Type Statistic Value
Biomass Boiler 499kW Herz Firematic
Previous Fuel Source Oil
Current Heat Usage 664,700kWh’s
Fuel Type Wood Chip
Fuel Usage 207 Tonnes
Back Up Boilers 2 x Oil boilers in the Hall
Back Up Boiler Fuel Oil
CO2 Savings per Year 207 Tonnes
Projected RHI Payment per Annum £34,166.53
Fuel Savings per Annum £14,145.00 (estimated)
Projected Payback Time 5 Years

Project Summary

The land agent was looking at reducing the heating costs for the Hall, tenanted buildings and offices, as well as providing an uplift in the heating capacity due to the limited size of the existing gas main.

As the estate had the capability of producing its own woodchip a 350kW Herz Firematic wood chip boiler with a 5,000ltr buffer was specified to provide the heat, with a back-up gas boiler connected to the buffer and metered for ineligible incentivised heat production.

A plant room was constructed within an existing farm building, with a new wood chip store constructed to the side of it. A district heat main was installed to carry the heat between the buildings, with a variable speed, temperature controlled shunt pump providing the heating control to each of the buildings.

J L Phillips designed, specified and installed the project within criteria set out by the client, the boiler is now providing heat to all buildings with the back-up boiler automatically engaging during maintenance, down time and wood chip fills.

Claim Your Free Quick Quote

Why not take a look at what a new renewable heating system might cost to install in your home or business. All we need is your preferred heating technology along with the approximate age and size of your property

Claim Quick Quote
01636 642790
info@jlphillips.co.uk
J L Phillips Renewable Energy Ltd, Fen Lane, Long Bennington, Newark, NG23 5ED